Overhaul and repair management of a strategic generator at a chemical works in Western Australia – paper

Published Jul 11th, 2022 IRMC 2022 - Vikas Bhandari

IRIS online Partial Discharge testing was performed as an integral part of condition based maintenance of a 6.6kV Shinko Generator at a chemical plant in Western Australia.
The generator has a double shaft, connected between a steam turbine prime mover and the main production compressor for the plant. The strategic nature of the compressor is such that if the generator failed, the compressor operation would be maintained using the generator rotor as a drive shaft.

DOWNLOAD ARTICLE (PDF)